  1. 2017 to 2019

    A footbridge for the Sun Chase trail. In April 2017 the Infrastructure Committee asks the engineer to review a bridge across the drainage channel in Sun Chase Park. On February 20, 2019 the district board approves $45,700 for a steel footbridge, 4-1. Director Zervigon† moves; Director Franke† seconds. Ayes: Franke†, Medrano, Norton Ramirez, Zervigon†. Director Rocco† asks "if there was a less expensive way to install the bridge." The engineer replies that a bridge of this span is hard to place without a pier. A pier is a risk to water flow in the channel. Director Rocco† votes no.

    Minutes, Apr 2017. Minutes, Feb 20 2019.
  2. Sep 11, 2019

    Budget list. The district's parks beautification list for fiscal year 2019-2020 has an item dated September 11, 2019: "Sunchase Playscape Removal (Need Estimate)." The amount set is $0.00. September 11, 2019 was the board's budget meeting. The minutes of that meeting do not mention the playscape.

    Bookkeeper's financial report, Feb 19 2020 board packet, "Project: Parks Beautification" table. Special meeting minutes, Sep 11 2019 (district archive copy).
  3. Jan 8, 2020

    The operator's report says the district's Parks Committee met on January 8 and "Discussed dismantle of Sun Chase Playscape - we have a potential school that is interested."

  4. Jan 15, 2020

    Manager's report. The playscape comes up under agenda item 7, the district manager's report. The minutes for item 7 say: "The Sun Chase park playscape will be dismantled and donated to a local school. Dir. Franke† envisions a new design for the space."

    On the recording, a speaker asks, "Is is the parks committee thinking about replacing it with something later?" The answer: "Yes, we are." The plan stated is to "remove uh the playscape in Sun and then we are going to come up with a different design for that space." Then: "The reason I ask is that there often are children on it." The replies include "But there's bigger parks down the road" and "We're thinking about doing something completely different, but we have to We're doing some research right now." Asked "You going to repurpose it?", a speaker answers: "Yes. We're repurposing the space." On its condition, one speaker says "It's usable." Asked whether it was worth $300 or more, another says, "I think it's going to cost us more than $300 to repair it or remove it." The item is put on the next agenda. No vote is taken.

  5. Feb 19, 2020

    Agenda. The agenda has 31 items. Item 12 is the "Report from the Parks Subcommittee." The playscape is item 30: "Declaring Sunchase playscape equipment as surplus property; authorization to sell Sunchase playscape equipment." (Surplus property is property the district no longer needs.)

    Agenda, Feb 19 2020, items 12 and 30.
  6. Feb 19, 2020

    Public comment. A resident tells the board that item 30 "has never been public publicly discussed" and that "Nobody in our neighborhood knows why this is happening." A speaker replies: "We've talked about it a few times. Yeah. Last couple of meetings." A question follows about which meeting discussed why it was being removed. The reply does not name a meeting.

  7. Feb 19, 2020

    Footbridge payment. The board authorizes payment of $48,700 to Westar Construction for "footbridge installation, side-channel grading, and silt removal" at Sun Chase Park, 5-0 (Zervigon† moves; Medrano seconds). It also allocates $250 for a Sun Chase bridge grand opening on March 7, 2020, 5-0 (Franke† moves; Norton Ramirez seconds). During the engineer's report, speakers discuss soil left from the bridge work. One says the contractor "accumulated a lot of soil from digging that that slope." Speakers suggest using it for a mound "by the picnic bench" at the back of the park, "like we did in the front of the park." Then: "Or we can have another mound when the playscape goes away. If it goes away."

    Minutes, Feb 19 2020, engineer's report and item 12. Meeting recording, about 0:23:00 to 0:25:35.
  8. Feb 19, 2020

    Discussion and vote. During the parks report, staff say the playscape will be donated to an elementary school and picked up that Saturday. On the recording a speaker then says, "We'll just jump to 30." The minutes record the two votes under item 12 and no action under item 30. The recording of this part runs about ten minutes. Points from the recording:

    • The reason given: the playscape is "very deteriorated and it's just not worth doing the maintenance and the upkeep on it." Speakers say some parts can no longer be replaced.
    • On safety: "we're sort of thinking it's becoming a safety hazard." A speaker says the district operator, Inframark, "looked at all the playscapes": "there was a visual inspection."
    • On cost, one speaker says: "I don't think we said it can't be fixed. I think we said that it's not worth fixing it because it would cost too much." The board minutes on file for Jan 2015 to Feb 2020 (Mar 2015 to Dec 2016 missing) record no repair estimate for this playscape.
    • On use, a speaker asks what to say "if somebody were to ask me why did we get rid of it." The replies include "we were going to replace it with with something else" and "We didn't we didn't like it anymore. It didn't serve its purpose."
    • Asked "What is it going to replace?", a speaker answers: "The parks committee has not decided yet." The plan stated is to "come up with a new project so to speak for that space ... in the future."
    • A speaker says the removal is "not going to cost us anything." A speaker replies, "I'm just concerned," and then, "we just declared something surplus because it's can't be fixed and it's worthless." A speaker asks whether a statute bars giving away used playground equipment. The reply: "I'm not aware of any prohibition." The motion is then reworded to add "as-is" and "no warranty."
    • Speakers say the other parks are already done: "We've already done Anderson Mill West Park," and also Lakeline Oaks, Hatch Pond and Aster Pass. One says, "This is a oneoff."

    Two motions pass 5-0, both moved by Director Franke† and seconded by Director Norton Ramirez: one declares the playscape surplus, and one donates it "as-is with no warranty" to Buck Holtz Elementary School. Ayes: Franke†, Medrano, Norton Ramirez, Rocco†, Zervigon†. The minutes also record: "Dir. Franke† noted that the playscape is damaged and it would be costly and difficult to repair."

    Minutes, Feb 19 2020, items 12 and 30. Board minutes Jan 2015 to Feb 2020 on file (Mar 2015 to Dec 2016 missing). Meeting recording, about 2:06:47 to 2:16:21.
  9. Feb 22, 2020 (scheduled)

    Scheduled pickup. The February 19 minutes say: "Ms. Hester said that the Sun Chase playscape will be donated to a nearby elementary school and is set to be taken away on Saturday." That Saturday was February 22. No record confirms the pickup date. On March 25 a resident refers to "the playground equipment that was removed."

    Meeting recording, Feb 19 2020, about 2:06:51 to 2:07:05. Minutes, Feb 19 2020, item 12. Meeting recording, Mar 25 2020, about 0:34:38.
  10. Mar 7, 2020

    Bridge grand opening. The board funded a $250 grand opening for the new Sun Chase footbridge on this date. Later meetings refer to the "bridge opening" and the "grand opening celebration."

    Minutes, Feb 19 2020, item 12. Meeting recordings, Mar 25 2020 (about 1:36) and Apr 15 2020 (about 0:21).
  11. By Mar 20, 2020

    COVID-19: parks closed. At a special meeting the operator explains that areas "where people tend to congregate (parks, basketball courts, tennis courts, etc.) are closed." On the recording: "our parks are closed. The equipment is closed."

    Special meeting minutes, Mar 20 2020. Meeting recording, Mar 20 2020, about 1:11 to 1:13.
  12. Mar 25, 2020

    HOA comment. The president of the Hunter's Glenn HOA tells the board that neighbors asked about "the playground equipment that was removed": "where did it go? What's happened?" She asks the district to "consider putting some sort of playground equipment in there for our children."

  13. Apr 15, 2020

    The operator reports caution tape "on all playscapes in accordance with the closing of the parks and libraries."

  14. May 20, 2020

    Bridge handrails. The board approves $8,200 to Westar Construction for entry handrails and concrete footers at the Sun Chase bridge. Director Medrano moves; Director Zervigon† seconds. On August 19, 2020 the engineer reports the handrails installed, and the board approves the $8,200 payment.

  15. By May 20, 2020

    First reopening. The operator reports that the tennis courts "have been reopened" with limits on players. Playgrounds are not part of this reopening.

    Minutes, May 20 2020; meeting recording, about 1:10:23.
  16. Jul 15, 2020

    Removal reported complete. During the accountant's report, a speaker tells the accountant that "the Sun [Chase] Playscape removal was completed and it didn't cost us anything." A speaker then adds, "We had a school come in and take it." The operator's monthly reports for March to July 2020 do not report the removal as done. The remark does not give the removal date.

    Meeting recording, Jul 15 2020, about 1:32:50 to 1:33:03. Manager's reports, Mar 25, Apr 15, May 20, Jun 17 and Jul 15 2020 board packets.
  17. Sep 16, 2020

    Vote to reopen playgrounds. The board votes to open district parks in "Phase II," including "playgrounds sanitized prior to opening." Director Norton Ramirez moves; Director Franke† seconds. Ayes: Franke†, Medrano, Norton Ramirez, Rocco†, Zervigon†. In October staff report that the playscapes at district parks were sanitized on September 25. A district news post dated September 24, 2020 says playgrounds would open on Saturday, September 26. Sun Chase has no play equipment at this time.

    Minutes, Sep 16 2020. Minutes, Oct 21 2020. District website news post "Playscape Equipment Sanitation," Sep 24 2020 (text in the wtcmud1.org post data).

Sources and corrections

Agendas, minutes and reports linked here are on the district website, wtcmud1.org. Quotes from meeting recordings come from unofficial auto-generated transcripts; check the time in the video before you quote them.

Corrections. If a fact here is wrong, use the form below and name the record that shows it. Errors will be fixed with the date of the change.